MRP in ERP and APS: Realistic Material Requirements Planning
-
How ERP systems and GANTTPLAN NOW connect material requirements planning with production planning
Material Requirements Planning (MRP) provides the material-related foundation for production planning. An MRP run can take place in an ERP system or in an APS system such as GANTTPLAN NOW. The decisive question is therefore not which system is fundamentally capable of MRP, but which tasks ERP and APS perform within an integrated planning process. This article explains the differences, how the two approaches can work together effectively, and when each is appropriate.
What is MRP?
MRP stands for Material Requirements Planning. The method determines which materials, components, and assemblies are required for production, the quantities needed, and the dates by which they must be available.
The starting point is independent demand such as customer orders, forecasts, or a production program. BOM explosion is used to derive dependent requirements for assemblies, individual parts, and raw materials. Inventory, open purchase orders, and planned production receipts are netted against these requirements.
An MRP run therefore primarily answers four questions:
- What material requirements arise?
- Which quantities are covered by inventory or planned receipts?
- Which materials must additionally be procured or produced?
- When must purchase orders or production orders become effective?
MRP aims to ensure material availability for production while avoiding unnecessary inventories. Material Requirements Planning is therefore an essential part of production planning, but it is not synonymous with production planning as a whole.
Key takeaway: MRP translates customer and production demand into time-phased, quantity-specific material requirements.
What role does MRP play in production planning?
A feasible production schedule requires both material and capacity to be available at the right time. An available machine is of no use if raw materials or components are missing. Conversely, available material does not automatically result in an executable schedule if machines, personnel, tools, or production resources are unavailable.
The MRP run therefore safeguards the material side of planning. It creates transparency regarding shortages, planned receipts, and dependencies between production stages. Scheduling and capacity planning must then connect this information with actual production conditions.
Multi-level relationships are particularly important: an upstream production order may supply material for a downstream order. If the first stage is delayed, not only a single operation but potentially the entire order network is shifted.
Key takeaway: MRP determines what is required and when. Production planning must additionally verify whether material and production resources are available at the same time.
How does the MRP run work in an ERP system?
The ERP system generally holds the authoritative commercial and logistics data. Customer demand, material master data, bills of materials, inventories, purchase orders, and planned and production orders are managed there.
A typical MRP run in ERP comprises the following steps:
- Import independent demand from customer orders, forecasts, or production programs.
- Explode bills of materials and determine dependent requirements.
- Net requirements against inventory and open receipts.
- Generate planned orders, production orders, purchase requisitions, or purchase order proposals for uncovered requirements.
- Provide and manage the planning results for procurement and production.
The strength of ERP-based MRP lies particularly in materials planning and the automated generation of procurement and production proposals. Various planning methods and parameters can be configured for individual materials. The extent to which capacities and dates are considered depends on the ERP system used, its configuration, and the company processes concerned. APS systems complement these functions with capacity-oriented detailed scheduling and optimization that considers resource and scheduling constraints.
Key takeaway: ERP MRP typically determines and manages what must be procured or produced and which planning objects are generated as a result.
Further reading:
Learn how an APS system complements existing ERP processes and extends production planning to include capacity and constraint planning: Make your ERP system fit for production with APS software!
How does GANTTPLAN NOW use MRP in production planning?
An APS system provides extensive MRP functionality. In GANTTPLAN NOW, the focus is on embedding Material Requirements Planning in a production-oriented planning process. Material is not considered in isolation, but together with dates, order dependencies, and finite resources.
Material supply objects and material demand objects
GANTTPLAN NOW distinguishes between material supply objects and material demand objects. Supply objects include inventory, supplier purchase orders, and upstream production orders. Demand objects include downstream production orders as well as customer demand or customer orders.
The MRP run establishes relationships between these objects. This reveals which inventory, purchase order, or production order can cover a requirement, at what time, and in what quantity. Existing material relationships can be imported, checked, and adjusted as required. Depending on the use case, GANTTPLAN NOW can import, supplement, or regenerate material relationships specified by the leading system, create order networks, or propose additional supply objects.
Planning material, dates, and capacities together
Material relationships feed into scheduling and resource planning. GANTTPLAN NOW considers the constraints stored in the planning model, such as machines, work centers, personnel, tools, production resources, and technological dependencies.
This enables planners to determine whether an order that is feasible from a material perspective can be completed on time under the available capacity conditions. It also shows when an order that is feasible from a capacity perspective is blocked by missing or delayed material. Depending on the process modelled, lot sizes, partial deliveries, and alternative supply objects can also be included in planning.
Key takeaway: GANTTPLAN NOW connects material supply and demand with the scheduling and allocation of finite production resources.
How do ERP MRP and MRP in GANTTPLAN NOW differ?
Both systems can use similar data and MRP functions. The main difference lies in their planning role within the overall process.
The distinction “ERP plans material, APS plans capacities” is too simplistic. More precisely, ERP primarily determines what must be procured or produced and which planning objects are generated. GANTTPLAN NOW additionally clarifies how material supply and demand objects are related and what executable schedule results when the modelled production conditions are taken into account.
Key takeaway: ERP MRP and APS MRP differ less in terms of a single function than in their role and depth of planning within the overall process.
How should ERP MRP and GANTTPLAN NOW work together?
The target state is not two duplicate, uncoordinated MRP runs, but an integrated ERP-APS planning loop. ERP and GANTTPLAN NOW perform different, complementary tasks. While ERP controls materials planning and operational processing, GANTTPLAN NOW provides capacity-oriented detailed scheduling. Continuous data exchange creates a realistic and consistent production schedule that considers material availability, capacities, and scheduling constraints in equal measure.
One possible integrated process:
A clearly defined division of system responsibilities is essential for this interaction. Companies must determine which system generates and maintains planning, production, or procurement proposals and which dates are authoritative. When these responsibilities are clearly assigned, a synchronized planning process is created in which ERP and APS operate on a shared data basis. This enables realistic dates, greater planning reliability, and better alignment between material and capacity planning.
Key takeaway: ERP and GANTTPLAN NOW should form a shared planning loop. Clear responsibilities prevent contradictory planning results.
Further reading:
When material availability and capacities are planned together, reliable delivery dates can also be determined. Find out how ATP and CTP support this process: Reliable delivery commitments with ATP and CTP in GANTTPLAN APS.
When is the MRP run in ERP sufficient?
An ERP-only MRP process may be sufficient if the ERP system reliably generates all required material relationships and the necessary production and procurement objects, while GANTTPLAN NOW performs detailed scheduling only for existing production orders.
Typical prerequisites are:
- Production orders and material relationships are created completely in the ERP system.
- The material availability check is already performed in the ERP system.
- GANTTPLAN NOW is not intended to generate additional planned, production, or procurement proposals.
- Sequences, resources, and dates are the focus in the APS system.
- Material relationships do not need to be adjusted during detailed scheduling.
In this scenario, GANTTPLAN NOW imports the provided production orders and the relevant scheduling, material, and resource constraints. An additional MRP run in the APS system is then not strictly necessary.
Key takeaway: An MRP run in ERP may be sufficient if the material side is fully prepared and the APS system is used exclusively for detailed scheduling.
Webcast “Ready for APS?”
The next available webcast will be available soon.
This webcast provides an in-depth insight into the principles and structure of APS systems. It explains how APS solutions differ from ERP and MES systems and highlights the role APS systems play in conjunction with them. We will focus in particular on the dos and don’ts of APS implementation and outline various key success factors.
Furter dates: Additional webcast slots will be available shortly.
When does MRP in GANTTPLAN provide additional value?
An MRP process managed or supplemented by GANTTPLAN NOW is particularly useful when materials planning in the ERP system is not sufficient to create a realistic production schedule.
Typical use cases include:
Multi-stage production: dependent production stages must be scheduled together as an order network.
High-variant manufacturing: supply objects, demand objects, or production routes can be assigned flexibly.
Bottleneck-oriented planning: material availability and scarce machine, personnel, or tool capacities must be evaluated together.
Dynamic supply: partial deliveries, alternative supply objects, or changed lot sizes affect planning.
Frequent changes: purchase-order shifts, new demand, or production disruptions require material and capacity to be realigned quickly.
Incomplete material relationships: data transferred from the ERP system must be checked or completed for production-oriented planning.
GANTTPLAN NOW does not need to fully replace the MRP run in ERP. The APS system can import the results of ERP MRP, process them further, and supplement them with selected Material Requirements Planning functions. The appropriate approach depends on the production structure, data quality, and required depth of planning.
Boosting machine utilization by 6.8 % with GANTTPLAN APS
A leading manufacturer of surface technologies and advanced materials increased its average machine utilization by 6.8% within one year using our APS system GANTTPLAN – now outperforming the industry benchmark.
This achievement stands out due to:
- exceptionally high quality standards (e.g. aerospace, semiconductors),
- complex, highly customized production processes,
- and the use of costly, specialized machinery where every additional hour of uptime makes a significant economic impact.
Key takeaway: Additional value is created where material relationships must be aligned directly with finite capacities and realistic production dates.
Frequently asked questions about MRP
What does MRP mean?
MRP stands for Material Requirements Planning. Based on requirements, bills of materials, inventories, and planned receipts, it determines which materials are needed, in what quantities, and by what date.
What data does an MRP run require?
Typical input data includes customer or production demand, material master data, bills of materials, inventory, open purchase orders, planned production receipts, procurement lead times, and production lead times.
Is MRP part of an ERP system?
MRP is a typical ERP function, but it is not technically limited to ERP systems. APS systems can also perform Material Requirements Planning or further process the results of an MRP run in ERP.
What is the difference between MRP and production planning?
MRP focuses on material quantities and requirement dates. Production planning additionally covers resources, capacities, order sequences, production alternatives, and specific start and finish dates.
When is an ERP system insufficient for production planning?
Additional planning capabilities are often required when material, multi-level order dependencies, and finite resources must be considered simultaneously or continuously realigned.
Do ERP and APS both need to run MRP?
No. Depending on the process, the MRP run may take place exclusively in ERP or be divided between the two systems. The decisive factor is a clear allocation of tasks and objects.
Key takeaway: The appropriate division between systems depends on the specific planning process, not on a blanket assignment of MRP to ERP or APS.
Conclusion: MRP as the link between material and production
MRP provides the material-related foundation for production planning. The MRP run can take place in an ERP system or in an APS system such as GANTTPLAN NOW. While ERP typically manages requirements, inventories, and supply objects, GANTTPLAN NOW connects material relationships with order networks, dates, and finite production resources.
The appropriate target state is not the parallel operation of two independent MRP runs. Companies should define which system generates which objects, performs which planning tasks, and exchanges which results. This turns materials planning into a realistic production schedule that can be used operationally.